Absorption and activity based costing: The use of absorption costing will include understanding relevant terminology: allocation, apportionment, absorption, under-absorption, over- absorption.
Absorption costing uses five linked terms.
- Point 2 of 9
Study notes
From the teaching notes for this specification point.
The idea
Absorption costing uses five linked terms. Allocation assigns a whole overhead cost to the single cost centre that clearly caused it, for example a department's own supervisor salary. Apportionment splits a shared overhead between several cost centres on a fair basis, such as floor area for rent or machine value for depreciation. Absorption then charges each unit a share of a cost centre's overhead using a rate per basis unit. The absorbed amount is compared with the actual overhead incurred: if actual overhead exceeds the amount absorbed, the result is under-absorption; if the amount absorbed exceeds actual overhead, the result is over-absorption. Under-absorption and over-absorption are usually caused by output or hours differing from the budgeted level used to set the rate.
What earns the marks
- Defines allocation as charging an entire overhead to the one cost centre that caused it.
- Defines apportionment as sharing a common overhead between cost centres using a fair basis such as floor area.
- Defines absorption as charging overhead to units through a predetermined rate per basis unit.
- Identifies under-absorption as the situation where overhead absorbed is less than the actual overhead incurred.
- Identifies over-absorption as the situation where overhead absorbed is greater than the actual overhead incurred.
Common mistakes and how to put them right
Uses allocation and apportionment interchangeably.
Put it right: Keep allocation for whole costs traceable to one centre and apportionment for shared costs split on a basis.
Reverses under-absorption and over-absorption.
Put it right: Compare absorbed overhead with actual overhead and state which is larger.
Treats apportionment as the final charge to the product.
Put it right: Apportionment only distributes overhead to cost centres, and absorption carries it to units.
Explains under-absorption or over-absorption as an arithmetic error only.
Put it right: Link it to actual activity differing from the budgeted activity used to set the rate.
Exam tips
- Learn each term with a one-line example so definitions can be applied rather than recited.
- When asked to classify a cost, ask whether it belongs wholly to one centre (allocation) or is shared (apportionment).
- For under-absorption and over-absorption questions, write the comparison as absorbed overhead against actual overhead before naming the result.
- Watch for the hyphenated spelling of under-absorption and over-absorption in written answers.
Try the lesson
The start of the Absorption and activity based costing: The use of absorption costing will include understanding relevant terminology: allocation, apportionment, absorption, under-absorption, over- absorption. lesson, made from teaching notes for this specification point.
Have a go first
A cost that can be charged directly and wholly to one specific cost centre is best described by which term?
There is more to this lesson
The full lesson goes on to check your understanding and help you earn the marks. Create a free account to carry on, with your progress saved.
A week of Premium from your first lesson · Then the free plan continues · No card, no charge
Test your understanding of Absorption and activity based costing: The use of absorption costing will include understanding relevant terminology: allocation, apportionment, absorption, under-absorption, over- absorption.
Active recall beats re-reading. Take an instant quiz now to test what you’ve learned and lock it into long-term memory.
A week of Premium from your first lesson · Then the free plan continues · No card, no charge