AQA · A-Level · Accounting

    Course version: 7127 · Version from Sept 2017

    Budgeting: labour

    In budgeting, labour is a cost that a business plans for before the period begins.

    • Point 12 of 14

    Study notes

    From the teaching notes for this specification point.

    The idea

    In budgeting, labour is a cost that a business plans for before the period begins. A labour budget converts planned production into the hours and the cost of the people needed to make it. The usual method is: take budgeted production in units, multiply by the standard hours per unit to give total standard hours, then multiply by the standard rate per hour to give budgeted labour cost. If production is 2,000 units, each needing 0.5 standard hours, total standard hours are 1,000; at a standard rate of £12 per hour the budgeted labour cost is £12,000. Learners must separate hours from money, keep the standard rate fixed for planning, and recognise that idle time, overtime premiums and wage-rate changes create variances when actual results are compared with the budget.

    What earns the marks

    • Calculates total standard hours by multiplying budgeted production units by the standard hours per unit.
    • Calculates budgeted labour cost by multiplying total standard hours by the standard rate per hour.
    • Distinguishes the labour hours figure from the labour cost figure and labels each correctly.
    • Explains that the standard rate per hour is the planned rate used for budgeting, not the actual rate paid.

    Common mistakes and how to put them right

    • Multiplies units by the rate per hour and ignores the hours per unit.

      Put it right: Insert the standard hours per unit step before applying the rate.

    • Treats the actual wage rate as the budgeted rate.

      Put it right: Use the standard rate for the budget and compare actual later as a variance.

    • Adds overtime premium into the standard rate without stating the assumption.

      Put it right: Keep the standard rate as planned and treat premiums separately.

    Exam tips

    • Write the three-step chain (units × hours per unit × rate per hour) before substituting numbers so the method is visible.
    • Label every figure with its unit, such as standard hours or £, to avoid mixing hours and cost.
    • Check the arithmetic by working backwards from the labour cost to the hours.

    Try the lesson

    The start of the Budgeting: labour lesson, made from teaching notes for this specification point.

    Have a go first

    Budgeted production is 1,200 units and each unit requires 2.5 labour hours. What is the total budgeted labour hours?

    There is more to this lesson

    The full lesson goes on to check your understanding and help you earn the marks. Create a free account to carry on, with your progress saved.

    Carry on with the full lesson

    A week of Premium from your first lesson · Then the free plan continues · No card, no charge

    Test your understanding of Budgeting: labour

    Active recall beats re-reading. Take an instant quiz now to test what you’ve learned and lock it into long-term memory.

    Take topic quiz

    A week of Premium from your first lesson · Then the free plan continues · No card, no charge