    Capital investment appraisal: net present value.

    Net present value (NPV) discounts every future net cash flow of a project back to today's value using a chosen discount rate, then subtracts the initial outlay.

    • Point 5 of 8

    Study notes

    From the teaching notes for this specification point.

    The idea

    Net present value (NPV) discounts every future net cash flow of a project back to today's value using a chosen discount rate, then subtracts the initial outlay. Multiply each year's net cash inflow by its discount factor, which equals 1 ÷ (1 + r)ⁿ where r is the discount rate as a decimal and n is the number of years ahead; add the discounted inflows and deduct the initial investment. A positive NPV means the project earns more than the required rate of return and adds value; a negative NPV means it falls short; between mutually exclusive projects, the higher NPV is preferred. NPV uses all cash flows and respects the time value of money, but it depends on the accuracy of the discount rate and cash-flow estimates.

    What earns the marks

    • Defines net present value as the sum of discounted future net cash flows minus the initial investment outlay.
    • Applies a discount factor of 1 ÷ (1 + r)ⁿ to each year's net cash inflow, where r is the discount rate as a decimal.
    • Adds the discounted inflows and deducts the initial outlay to reach the NPV figure.
    • Accepts a project with a positive NPV and rejects one with a negative NPV.
    • Selects the project with the higher NPV when choosing between mutually exclusive options.
    • Recognises that NPV uses all project cash flows and accounts for the time value of money.

    Common mistakes and how to put them right

    • Adds undiscounted cash flows and calls the total the NPV.

      Put it right: Discount each year's inflow before summing.

    • Forgets to deduct the initial outlay from the discounted inflows.

      Put it right: Subtract the outlay to obtain the NPV.

    • Uses the discount rate as a percentage in the formula instead of a decimal.

      Put it right: Convert it before calculating.

    • Rejects a project with a positive NPV.

      Put it right: Accept projects that add value above the required return.

    Exam tips

    • Write the discount factor formula and show each year's discounted value in a table.
    • State clearly whether the NPV is positive or negative and what that means for the decision.
    • Comment on the sensitivity of the result to the discount rate and cash-flow estimates.

    Try the lesson

    The start of the Capital investment appraisal: net present value. lesson, made from teaching notes for this specification point.

    Have a go first

    A project has a present value of future cash inflows of £90,000 and an initial investment of £70,000. What is its net present value?

    There is more to this lesson

    The full lesson goes on to check your understanding and help you earn the marks. Create a free account to carry on, with your progress saved.

    Carry on with the full lesson

    A week of Premium from your first lesson · Then the free plan continues · No card, no charge

    Test your understanding of Capital investment appraisal: net present value.

    Active recall beats re-reading. Take an instant quiz now to test what you’ve learned and lock it into long-term memory.

    Take topic quiz

    A week of Premium from your first lesson · Then the free plan continues · No card, no charge