AQA · A-Level · Accounting

    Course version: 7127 · Version from Sept 2017

    Standard costing and variance analysis: budget and actual cost

    In standard costing you compare what a cost should have been with what it actually was.

    • Point 9 of 10

    Study notes

    From the teaching notes for this specification point.

    The idea

    In standard costing you compare what a cost should have been with what it actually was. The budgeted (standard) cost is the allowed cost for the actual output: standard quantity per unit multiplied by standard price per unit, then multiplied by the number of units produced. The actual cost is the amount really paid: actual quantity used multiplied by actual price paid. The difference between the two totals is the total variance, and it is split into a price variance and a usage (quantity) variance so managers can see whether the cause is paying more per unit of input or using more input than allowed.

    For example: If the standard is 2 kg at £5 per kg for 1,000 units, the allowed cost is 2,000 kg × £5 = £10,000; if 2,100 kg were bought at £4.80 per kg, actual cost is £10,080, an adverse total variance of £80.

    What earns the marks

    • Identifies the budgeted cost as standard quantity per unit multiplied by standard price per unit and then by actual output.
    • Identifies the actual cost as actual quantity of input multiplied by the actual price paid.
    • Calculates the total variance as the difference between budgeted cost and actual cost and labels it favourable or adverse.
    • Splits the total variance into a price variance and a usage variance to explain the cause.

    Common mistakes and how to put them right

    • Multiplies the standard cost by budgeted output instead of actual output.

      Put it right: Use actual output so the allowance matches what was really produced.

    • Compares actual cost with the previous period's cost rather than the standard allowance.

      Put it right: Compare against the standard for the actual output.

    • Omits the favourable or adverse label.

      Put it right: State the direction of the variance explicitly.

    Exam tips

    • Write the standard allowance and the actual cost as two separate lines before subtracting, so the arithmetic is visible.
    • Check the sign convention: actual cost above standard is adverse, below standard is favourable.
    • State which element, price or usage, drives the total variance when the question asks for a cause.

    Try the lesson

    The start of the Standard costing and variance analysis: budget and actual cost lesson, made from teaching notes for this specification point.

    Have a go first

    A firm budgeted to produce 2,000 units at a standard material cost of £6 per unit. It actually produced 2,000 units and actual material cost was £13,000. What is the total material variance?

    There is more to this lesson

    The full lesson goes on to check your understanding and help you earn the marks. Create a free account to carry on, with your progress saved.

    Carry on with the full lesson

    A week of Premium from your first lesson · Then the free plan continues · No card, no charge

    Test your understanding of Standard costing and variance analysis: budget and actual cost

    Active recall beats re-reading. Take an instant quiz now to test what you’ve learned and lock it into long-term memory.

    Take topic quiz

    A week of Premium from your first lesson · Then the free plan continues · No card, no charge