Standard costing and variance analysis: labour (efficiency and rate)
Labour variances split total labour cost variance into an efficiency element and a rate element.
- Point 5 of 10
Study notes
From the teaching notes for this specification point.
The idea
Labour variances split total labour cost variance into an efficiency element and a rate element. The rate variance isolates the effect of paying a different hourly rate from standard: (standard rate − actual rate) × actual hours paid. The efficiency variance isolates the effect of using more or fewer hours than the standard allowed for output: (standard hours for actual output − actual hours worked) × standard rate. Worked example: standard rate £12 per hour, actual rate £13 per hour, actual hours 246, standard hours for output 240. Rate variance = (12 − 13) × 246 = £246 adverse. Efficiency variance = (240 − 246) × 12 = £72 adverse. Total = £318 adverse. Note the rate variance uses actual hours, never standard hours.
What earns the marks
- Uses actual hours as the multiplier when computing the labour rate variance.
- Applies the standard rate as the multiplier when computing the labour efficiency variance.
- Compares standard hours for actual output with actual hours worked to derive the efficiency variance.
- Labels an adverse rate variance when the actual rate exceeds the standard rate.
- Labels a favourable efficiency variance when actual hours fall below standard hours for output.
- Separates the total labour cost variance into its rate and efficiency components.
Common mistakes and how to put them right
Multiplies the rate difference by standard hours instead of actual hours.
Put it right: Use actual hours paid in the rate variance.
Treats the whole labour cost variance as the rate variance.
Put it right: Split it into rate and efficiency elements.
Reverses the sign so a higher actual rate is called favourable.
Put it right: A higher actual rate gives an adverse rate variance.
Compares actual hours with budgeted hours rather than standard hours for actual output.
Put it right: Use standard hours for actual output in the efficiency variance.
Exam tips
- Write the formula first, then substitute figures, so the examiner sees which hours and which rate you used.
- State adverse or favourable explicitly for each variance, not just the money amount.
- Check the two variances sum to the total labour cost variance as a self-check.
- Read the question for whether hours given are hours paid or hours worked before choosing the multiplier.
Try the lesson
The start of the Standard costing and variance analysis: labour (efficiency and rate) lesson, made from teaching notes for this specification point.
Have a go first
A job should take 40 labour hours at a standard rate of £8 per hour. It actually took 44 hours. What is the labour efficiency variance?
There is more to this lesson
The full lesson goes on to check your understanding and help you earn the marks. Create a free account to carry on, with your progress saved.
A week of Premium from your first lesson · Then the free plan continues · No card, no charge
Test your understanding of Standard costing and variance analysis: labour (efficiency and rate)