AQA · A-Level · Business
Course version: 7132 · Version from Sept 2023
The value of network analysis in strategic implementation (to include:…
Full specification wording
Managing strategic implementation: The value of network analysis in strategic implementation (to include: Network analysis to include: understanding and interpreting network diagrams, amendment of network diagrams, identifying the critical path and total float.)
A network diagram sets out every activity in a project, how long each takes and what has to finish before each can start, and its payoff is a completion date the business can actually commit to.
- Point 3 of 3
- 4 key terms
Study notes
From the teaching notes for this specification point.
The idea
A network diagram sets out every activity in a project, how long each takes and what has to finish before each can start, and its payoff is a completion date the business can actually commit to. The forward pass carries earliest start times through the diagram, taking the highest figure where paths meet; the backward pass brings latest finish times back, taking the lowest. The chain with no spare time is the critical path, and it fixes the minimum duration, so a day lost on it is a day lost on the whole project. Total float, the latest finish time of an activity minus its duration minus its earliest start time, measured in days, tells a manager how much slack a non critical job has and therefore where labour can safely be taken from. It is blind to cost, to quality, and to whether the estimated durations were honest.
What earns the marks
- Reading the diagram correctly, earliest start times from the forward pass taking the highest incoming figure, latest finish times from the backward pass taking the lowest.
- Identifying the critical path as the activities carrying zero total float and stating the minimum project duration in days from the final node.
- Calculating total float for a named activity as latest finish time minus duration minus earliest start time, then interpreting it, such as saying the delivery can slip four days without moving handover.
- Amending the network when the case changes a duration, recalculating both passes and saying whether the completion date moves or the delay is absorbed by float.
- Using the result in a decision, such as ordering materials to arrive at an activity's earliest start time to cut holding costs, or moving staff off a floated task onto a critical one.
Common mistakes and how to put them right
Taking the lowest figure on the forward pass and the highest on the backward pass, which reverses the logic and produces floats that are negative or simply impossible.
Adding every activity duration together and calling the total the critical path, which ignores the activities that run in parallel.
Assuming any delay delays the project, when a slip smaller than an activity's float changes nothing, and the mirror error of spending the same float twice along one path.
Treating estimated durations as facts, so the answer offers no evaluation of the assumption the whole diagram rests on.
Exam tips
- Network questions arrive as calculate and analyse, so do the working on the diagram itself and then write the sentence that says what the number means for the business.
- Amendment is the discriminator, so redo both passes after a change rather than guessing, because a different critical path often appears once an activity is extended.
Try the lesson
The start of the Managing strategic implementation: The value of network analysis in strategic implementation (to include: Network analysis to include: understanding and interpreting network diagrams, amendment of network diagrams, identifying the critical path and total float.) lesson, made from teaching notes for this specification point.
Have a go first
In network analysis, what name is given to the longest sequence of dependent activities through a network diagram?
Listen
A network diagram sets out every activity in a project, how long each takes and what has to finish before each can start, and its payoff is a completion date the business can actually commit to. The forward pass carries earliest start times through the diagram, taking the highest figure where paths meet; the backward pass brings latest finish times back, taking the lowest. The chain with no spare time is the critical path, and it fixes the minimum duration, so a day lost on it is a day lost on the whole project. Total float, the latest finish time of an activity minus its duration minus its earliest start time, measured in days, tells a manager how much slack a non critical job has and therefore where labour can safely be taken from. It is blind to cost, to quality, and to whether the estimated durations were honest. A strong answer earns marks for these points. Reading the diagram correctly, earliest start times from the forward pass taking the highest incoming figure, latest finish times from the backward pass taking the lowest. Identifying the critical path as the activities carrying zero total float and stating the minimum project duration in days from the final node. Calculating total float for a named activity as latest finish time minus duration minus earliest start time, then interpreting it, such as saying the delivery can slip four days without moving handover. Amending the network when the case changes a duration, recalculating both passes and saying whether the completion date moves or the delay is absorbed by float. Exam tip: Network questions arrive as calculate and analyse, so do the working on the diagram itself and then write the sentence that says what the number means for the business.
Key words
Say what each word means before you turn the card.
critical path
Try answering aloud or in your head before turning the card.
earliest start and latest finish times
Try answering aloud or in your head before turning the card.
total float
Try answering aloud or in your head before turning the card.
amending a network
Try answering aloud or in your head before turning the card.
See every definition
- critical path
- The chain with no spare time, which fixes the minimum duration, so a day lost on it is a day lost on the whole project.
- earliest start and latest finish times
- Carried through the diagram by the forward pass taking the highest figure where paths meet and the backward pass taking the lowest.
- total float
- The latest finish time of an activity minus its duration minus its earliest start time, measured in days, showing how much slack a non critical job has.
- amending a network
- Recalculating both passes when the case changes a duration and saying whether the completion date moves or the delay is absorbed by float.
There is more to this lesson
The full lesson goes on to check your understanding and help you earn the marks. Create a free account to carry on, with your progress saved.
A week of Premium from your first lesson · Then the free plan continues · No card, no charge
Test your understanding of Managing strategic implementation: The value of network analysis in strategic implementation (to include: Network analysis to include: understanding and interpreting network diagrams, amendment of network diagrams, identifying the critical path and total float.)
Active recall beats re-reading. Take an instant quiz now to test what you’ve learned and lock it into long-term memory.